Our Contacts

Building 18 Office Park Lt. 18
Jl. T.B. Simatupang No.18, Pasar Minggu,
South Jakarta - 12520
Indonesia

info@plnnpc.com

+62 (021) 2787 1818
+62 (021) 2770 8558

Read More

Trasmission Line 150 kV Piru – Kairatu

This time PT Rekadaya Elektrika (RE) will review the progress of the work of one of the transmission projects located in Central Maluku and Seram districts, namely the Piru-Kairatu 150 kV Transmission Line.

The electricity infrastructure project owned by PLN UPP Maluku which is entrusted to Rekadaya Elektrika, will later combine 2 (two) Piru Substations (GI) and Kairatu GI, with a total of 123 towers.

As of the 2nd week of January, work progress had reached 45.487% (leading) where land clearing and foundation construction work had progressed significantly.
The total installed foundations are currently 72 foundations (of the target of 123 foundations), with a transmission line of 91 kms. TL 150 kV Piru – Kairatu is planned to be energized at the end of 2023.

Like the projects that Rekadaya Elektrika has worked on, the Piru-Kairatu TL project also faced several technical problems in the field during the construction process. Such as access to material alerts which is difficult because of the hilly terrain and high rainfall in the last few months.

However, the RE Project Team continues to strive and provide the best results to achieve progress in the construction of this transmission line, so that it can immediately meet the electricity needs on Seram Island, Maluku. Electrical Rekadaya will always play an active role and make a real contribution in building and increasing the reliability of the electricity system throughout Indonesia.

Read More

PT Rekadaya Elektrika Has Successfully Completed The Construction Of Unit 1 of the Relocation PLTG Batanghari to East Halmahera.

Closing 2022, PT Rekadaya Elektrika (RE) has successfully completed the relocation project for unit 1 of the Batanghari Gas Power Plant (PLTG) to East Halmahera Island. This PLTG with a total capacity of 111 MW is the second power plant relocation project that was successfully completed by RE.

The East Halmahera PLTG, which is a relocation of the Jakabaring PLTG (3×17 MW) and the Batanghari PLTG (2×30 MW), is a form of synergy with the PLN Group (together with PLN NP, Rekadaya Elektrika and PJBS) as a form of support for the National Strategic Program, namely to ensure the reliability of the supply of electrical energy for the operational activities of the ferronickel smelter owned by PT Aneka Tambang (ANTAM) which is located in the Maluku islands.

The Electrical Engineering project team led by the Project Manager, namely Yehuda Keyzia, succeeded in completing the scope of work that was RE’s responsibility within 6 months. This moment was witnessed directly by the Board of Directors of PT Rekadaya Elektrika represented by Mr Jonner MP Pardosi as Main Director, Mr Indrayoga Suharto as Business Director I, Mr Nur Hidayat as Business Director II and the entire joint team from RE and the PLN Group.

Also attending the event and joining online were Mr. Darmawan Prasodjo as the Main Director of PT PLN (Persero), Mr. Adi Lumakso as the Director of Generation Management of PT PLN (Persero), Mr. Ruly Firmansyah as the Main Director of PT PLN Nusantara Power and Mr. Dolok Robert Siahaan as Director of Business Development of PT ANTAM.