Project Trasmission Line 70 kV GI Namrole-Namlea
Still
around Eastern Indonesia, this time we will visit South Buru Island-Maluku, the
location of one of the transmission line projects being worked on by PT
Rekadaya Elektrika (RE). The 70 kV Namrole – Namlea Transmission Line project
will connect two substations (GI), namely Namrole GI and Namlea GI, which cross
7 villages with a total distance of 90.3 kilometers.
Entering
the end of January, the overall progress of the work has reached 84.12%
(leading from the target of 80.77%). Currently, the total land that has been
acquired has reached 93.16%, with a total of 216 foundations that have been
completed, of the target of 234 tower foundations (92.31%). (72.65%).
The
Namrole-Namlea 70 kV TL Project is also not free from a number of technical and
non-technical challenges. One of the obstacles faced was the rocky location of
the land, which made it difficult for the field team to work. However, the team
in the field has exerted maximum effort, including using jack hammers and heavy
equipment (excavators) to level the roads and the foundation construction
sites.
The
RE project team continues to make progress in the construction of this
transmission line, so that it can immediately meet the electricity needs of the
people on South Buru Island, Maluku.