Progress Pembangunan PLTS PT Pertamina Power Indonesia

Since the execution of the contract signing (work order-WO) on 04 October 2022, currently the progress of PT Pertamina Power Indonesia’s internal PLTS development work for clusters 3, 4 and 5 is almost complete. The progress of work in the field for the two clusters has reached 95% and is ready to operate.

As of March 3 2023, the three clusters that are being worked on by PT Rekadaya Elektrika are:

Cluster 3  :

  • PGN-Ketapang office building, West Jakarta with a total capacity of 36,000 Wp;

  • Pertamina Central Hospital located in South Jakarta with a capacity of 120,000 Wp

  • Pelita Air Service Pondok Cabe, South Tangerang (2 location points) with a total capacity of 100,000 Wp

Cluster 4 :

  • Pertamina Trans Kontinental – Kabil in Batam City, Riau Archipelago with a total capacity of 12,000 Wp

Cluster 5 :

  • Pertamina Geothermal Energy – Lahendong in Tomohon, North Sulawesi with a total capacity of 20+20 kWp.

Rekadaya Elektrika through the project team in the field continues to contribute to developing renewable energy through the construction of new renewable energy-based power plants.

 