This time, REINISTE will raise a story about one of the Availability Improvement Program (AIP) jobs that is currently almost completed by the Rekadaya Elektrika (RE) project team, namely the Procurement Work of the Feed Water Pipe Bypass Line Modification and Steam Drain High Preassure Heater (HPH) owned by PT PLN Nusantara Power Tanjung Awar-awar Generating Unit located in Tuban, East Java.
It is said to be almost complete, because currently the progress of work which includes mechanical, instrument and electrical work which is the responsibility of RE has reached 100%. And currently leaving the commissioning work, namely RR or Reability Run for 2×24 hours at maximum load to ensure the feasibility of operation of the HPH Feed Water and Steam Drain pipe installations and the implementation of operational training.