WORK PROGRESS RELOCATION PLTG EAST HALMAHERA 111 MW

default

After at the end of 2022, the PT Rekadaya Elektrika project team successfully completed the construction of 2 units of the East Halmahera Gas Power Plant (PLTG), now 3 other generating units are also being accelerated so that they can operate immediately.

The PLTG owned by PT PLN (Persero), which was relocated from the Sumatra region (Jakabaring and Batanghari), will aim to supply electrical energy for PT Aneka Tambang’s ferronickel smelter activities in East Halmahera. With a total capacity of 111 MW consisting of 5 generating units.

As of the end of April the work progress has reached 89%, with the scope of work currently being completed is civil construction work, electrical work (including installation of Transformers, MV Panels, LV Panels and Batteries) and mechanical work (including Water Treatment Plant, Waste Water Treatment Plant, and Fire Fighting).